Program design
A builder with a pipeline does not want to arrange a new wrap-up every time a project starts. A rolling program solves that, and introduces one problem the single-project version does not have.
One of four program design decisions.
A rolling wrap-up is a single program that projects are added to as they start, under eligibility criteria agreed with the carrier up front. It saves the sponsor from marketing a new program every time.
The catch is the limit. Unless each project is given its own dedicated limit, every job in the program is drawing on the same tower, and a bad loss on one project can leave the others short.
Whether that matters depends on how many projects are in the program, what they are worth, and how long the tail runs after each one closes.
Three arrangements
Sponsors ask for one program across several projects for an obvious reason. Marketing a new wrap-up every time a job starts is slow, and a builder with a pipeline cannot run that process four times a year. But "several projects in one program" describes at least three different arrangements, and they behave very differently.
| Arrangement | How projects join | Limits | Suits |
|---|---|---|---|
| Phased single project | Phases of one development, known at placement | Normally one shared tower | A large site built in stages over several years |
| Rolling wrap-up | Added as they start, under eligibility criteria agreed in advance | Shared by default, dedicated by negotiation | A continuous pipeline of similar projects |
| Scheduled multi-project | A fixed list of named projects, all known at placement | Either, and easier to dedicate because the list is closed | Two or three jobs starting around the same time |
The scheduled version is the simplest, because everything is known when the program is marketed. The rolling version is the one most repeat builders actually want, and the one with the most to get wrong.
The main problem
If several projects sit under one program with one aggregate limit, every project is drawing on the same tower. A serious loss on the first job reduces what is available to the rest, and on a program with a long completed operations tail that erosion can keep happening for years after the project that caused it was finished and sold.
That is more than a theoretical problem on residential work. One defect action on one building, with twenty trades and experts on both sides, can consume a meaningful share of a shared aggregate in defense costs alone before any damages are paid. The remaining projects in the program then have less coverage than their lenders, their contracts or their buyers were told they had.
There are three ways to deal with it, and they cost different amounts.
Whichever is chosen, the number people care about is the one described on the California rules page as a statutory disclosure: on a California residential program covering more than one project, the contract documents have to address the number of units and a good faith estimate of the limits still available. A subcontractor joining the fourth project in a rolling program is entitled to know what is left.
Getting it right
A rolling program works because the carrier has agreed in advance what kinds of project can be added without new underwriting. Those criteria are negotiated once, at placement, and they govern the program for its life. Typical dimensions:
That last point is the operational risk. A project that starts without being notified may not be in the program at all, and the discovery usually comes later. The notification process needs an owner inside the organization, and the eligibility criteria need to be in front of whoever is starting projects, not filed with the insurance documents.
Projects that fall outside the criteria are not disasters. They are placed separately, as their own wrap or on another structure. The problem is only when somebody assumes they are inside and nobody checks.
Timing
Each project has its own completion date, so each one has its own completed operations period. A program that adds projects over four years and carries a ten-year tail is still responding to claims fourteen years after it started.
Three questions follow from that.
Does the tail run per project or from the close of the program? Per project is the more common and the more logical. From the close of the program is more generous to the early projects and should be priced as such.
What happens if the program is not renewed? Projects already added should keep their completed operations coverage. That needs to be explicit, because a sponsor who moves to another carrier in year five and finds the first four years of projects are no longer covered has a problem with no remedy.
Who is tracking it? Fourteen years is longer than most project teams, and often longer than the relationship with the broker who placed it. Somebody needs a record of which projects are in the program, when each one completed, and when each tail expires. See the policy term page for what else that record should carry.
Questions
A single wrap-up program that projects are added to as they start, under eligibility criteria agreed with the carrier in advance. It saves a repeat builder from marketing a new program for every job, at the cost of introducing a shared limit question that a single-project program does not have.
By default yes, which means a serious loss on one project reduces what is available to the others, potentially for years afterwards. Project-dedicated limits inside the rolling program solve it and cost more. A reinstating aggregate is a middle position. On for-sale residential the dedicated version is usually worth the money.
The eligibility criteria negotiated at placement: maximum construction value, permitted scopes, construction type and height, tenure, geography, maximum duration, and the notification process. A project outside the criteria is placed separately, which is fine. The risk is a project that falls outside and nobody notices.
Usually at that project's own completion, so each project runs its own clock. Some programs instead start every tail at the close of the program, which is more generous to the earlier projects. It is worth confirming which, because the difference can be several years.
Projects already added should keep their completed operations coverage for the agreed term. That should be explicit in the program documents rather than assumed, because a sponsor who moves to another carrier and finds the earlier projects uncovered has no way to fix it after the fact.
On a private residential program covering more than one project, Civil Code 2782.95 requires the contract documents to address the number of units covered and a good faith estimate of the limits still available under the program, along with the limits, scope, term and deductible trigger. A participant joining a later project is entitled to know what is left.
Next
The other three design decisions.
Who you would be working with
Managing Director · ISU Insurance Services of San Francisco
Cary handles the wrap-up placements here. He has spent 38 years in construction insurance. The first ten were on the carrier side, underwriting builders’ risk and complex property exposures. The 28 since have been in retail brokerage, advising residential developers, general contractors and other construction clients on project-specific and annual programs.
He is also one of the original authors of the project liability application that much of the industry still uses to submit wrap-ups to carriers. In practice that means he knows what each question is actually asking for, and where a thin answer will cost you at quote.
Pricing
Tell us about the project and we will give you a straight answer on whether a wrap makes sense for it. If it does not, we will say so, and then we will price the structure that does. That answer is worth more to you than a placement that costs more than it saves. There is no project minimum to ask. This goes straight to Cary White, who handles wrap-up placements for our construction clients.